Crews two months behind on construction of I75 corridor
With weather playing a big factor, MDOT has notified its scheduled shift of northbound traffic to its new northbound lanes will now happen at the end of the year, instead of by Thanksgiving. Crews have lost about 60 workdays because of bad weather.